Daytona Rising April Project Update:

During the recent weeks, Daytona International Speedway continued demolition of the Sprint Tower as part of the $400 million DAYTONA Rising redevelopment project. Using a 490-foot Manitowoc 2250 Crawler Crane, the Speedway has already completed the removal of the Tower’s iconic front faƒÃ‚§ade that featured “DAYTONA.” The Speedway will continue the 30-day demolition process with two additional phases. The next phases will involve the removal of elevated walkways and concessions between the Tower and the Speedway followed by general demolition of the Campbell Suites. Additional upcoming construction activities include: Ongoing elevator installation, Continuing miscellaneous framing and concrete installation, and Developing hospitality suites.(DIS)(4-8-2015)